2005 Past Project Experience
- ADO CIMENTO SAN. TIC. A.S. / 2004 – 2005
Kızılkaya Cement Plant
- Clinker Production Line
17.1. Maintenance and erection of the rotary kiln together with it’s
all equipments ( Polysius – Ø 4,2 x 60 m ).
17.2. Installation of the coal mill unit and fabrication of the local equipments (PFEIFFER ).
17.3. Installation of the Clinker cooler unit and fabrication of the local equipments ( IKN ).
Weight of the local fabrication works: 650 ton
Weight of the erection works: 1350 ton
- BETONSAN – BETON VE CIMENTO SAN. A.S. / 2005
Lalahan Cement Grinding Facility
18.1. Alignment works for the gear box and bearings of the Cement mill.
- VICAT – KONYA CIMENTO SAN. A.S. / 2005
Konya Cement Plant
19.1. Both Fabrication and installation works for the raw metarial feeding line
of the Raw mill.
Weight of the local fabrication works: 350 ton
Weight of the erection works: 600 ton
- DENIZLI CIMENTO SAN. TIC. A.S. / 2005
Denizli Cement Plant
20.1. Revision of the ESP number II (Changing of the discharge electrodes,
maintenace of the hammers e.t.c.).
20.2. Replacement of the light kiln shell, heavy kiln shell with tyre, rollers and
adjustment of the gear and drive unit for the rotary kiln number II.
- CIMENTAS KARS CIMENTO SAN. TİC. A.Ş. / 2005
Kars Cement Plant
21.1. General revision works for clinker cooler, crusher, raw and coal mill e.t.c.
- CIMSA CIMENTO SAN. TIC. A.S. / 2005
Kayseri Cement Plant
22.1. Erection of the Rotary Kiln ( FLS – Ø 3,6 x 55 m ).
- IZAYDAS IZMIT ATIK VE ARTIKLARI DEGERLENDIRME A.S. / 2005
23.1. Revision of the rotary kiln ( Ø 4,2 x 12 m ).
- ADO CIMENTO SAN. A.S. / 2005
Antalya Cement Grinding Facility
24.1. Replacement of gears for the gearbox of the cement.