2007 Past Project Experience
- YIBITAS LAFARGE ORTA ANADOLU CIMENTO SAN. TIC. A.S. / 2007
Corum Cement Plant
30.1. Fabrication and installation works for the modification works of the clinker cooler.
Weight of the local fabrication works: 35 ton
Weight of the erection works: 90 ton
- OYAK – MARDIN CIMENTO SAN. TIC. A.S. ( DAL TEKNIK ) / 2007
Mardin Cement Plant
31.1. Erection of the Rotary Kiln Unit ( HUMBOLDT – Ø 4,33 x 65 m ).
31.2. Fabrication of the cyclones located on preheater tower ( OMAG ).
Weight of the local fabrication works: 550 ton
Weight of the erection works: 900 ton
- OYAK BOLU ÇIMENTO SAN. A.S. / 2007
Saraykoy Grinding Facility
32.1. Replacement of the trunnion for cement mill.
- VICAT – KONYA CIMENTO SAN. A.S. / 2007
Konya Cement Plant
33.1. Fabrication and replacement of the beams for the raw mill.
(Loesche – LM 45-4 )
- VICAT – KONYA CIMENTO SAN. A.S. / 2006 – 2007
Konya Cement Plant
34.1. Installation of the cement mill unit (FCB – Horomill-2 / Ø 3800 ).
Weight of the local fabrication works: 1200 ton
Weight of the erection works: 2100 ton
- SANKO – CIMKO CIMENTO FABRIKASI ( EKON – PROKON ) / 2007
Kahramanmaras Cement Plant
35.1. Installation of the rotary kiln unit.( Polysius – Ø 5,6 x 87 m )
35.2. Installation of the raw mill. (Polysius – RM 51 / 26 ) - ( 3 units )
35.3. Installation of the coal mill unit (Polysius – RMK 25 / 12) - ( 2 Units )
35.4. Installation of the other equipments Fans / Elevators
Weight of the erection works: 5500 ton
- AS CIMENTO SAN. TIC. A.S. / 2007
Kızılkaya Cement Plant
36.1. Replacement of the kiln shell for rotary kiln number I.
(Polysius – Ø 4,0 x 60 m )
- VICAT – BASTAS BASKENT CIMENTO SAN. TIC. A.S. / 2007
Bastas Cement Plant
37.1. Replacement of the seperator of the raw mill named Loesche LM 45-4 and some revision works.