2013 Past Project Experience
- RENAISSANCE CONSTRUCTION – RUSYA / 2012 – 2013 ( NORM-CCM )
Sebryakov Cement Plant - Mihailovka
98.1. Fabrication and installation of the clinker production line ( 4000 Tpd. )
Site Fabrication
98.2. Fabrication of the cyclones and ducts: 1250 ton
Workshop Fabrication
98.3. Fabrication of the some equipments in our workshop located on
Ankara-TURKEY ( Light kiln sections of the rotary kiln,
Stacker-Reclaimer, Apron conveyor, belt conveyors: 600 ton).
Erection
98.4. Erection of the raw mill unit.
98.5. Erection of the equipments in preheater tower.
98.6. Erection of the rotary kiln unit.
98.7. Erection of the clinker cooler unit and electrostatic precipitator for
clinker cooler.
98.8. Erection of the electrostatic precipitator for raw mill.
- RENAISSANCE CONSTRUCTION – RUSYA / 2012 – 2013 ( NORM-CCM )
Novocement Cement Plant-Novorosisky
99.1. Installation of the some units for clinker production line ( 4000 Tpd. )
Total weight of the installation: 3000 ton.
- KIPAS KAHRAMANMARAS CIMENTO SAN. TIC. A.S. / 2012 - 2013 - 2014
Kahramanmaras Cement Plant
Fabrication and installation works for the clinker production line number II.
100.1. Fabrication of the steel structure: 6500 ton
100.2. Fabrication of the technological equipments: 4000 ton
(Casing of the filters, some parts for the clinker cooler, cyclones,
. hoppers, gas ducts, chimney e.t.c. )
100.3. Fabrication of the mechanical Equipments: 1500 ton
(Casing of the coal, cement and raw mills, seperators, base frame of
the rollers for the rotary kiln, base frame of the roller press and their
accessories, valves, expansion joints, air slides and e.t.c.)
Total weight of the installation works: 15000 ton
Insulation works: 20 000 m2
Cladding works: 35 000 m2
100.4. General installation works for air, water and lubrication.
- DENIZLI CIMENTO SAN. TIC. A.S. / 2012
Denizli Cement Plant
101.1. Cladding works for the roof of the cement silo
Weight of the fabrication works: 46 ton
Weight of the installation works: 46 ton
Weight of the dismounting works: 5 ton
Cladding of the roof: 600m²
- RENAISSANCE CONSTRUCTION – RUSYA / 2012 – 2013 ( NORM-CCM )
Novocement Cement Plant-Novorosisky
102.1. Installation of the some units for clinker production line ( 4000 Tpd. )
Total weight of the installation: 3000 ton.
- CTP TEAM - S. KOREA / 2013
IGCC Gasfication Plant – Taean Project
103.1. Fabrication Mill Bag Filter Plenums
Weight of the fabrication works: 75 ton
- CIMSA CIMENTO SAN. VE TIC. A.S. / 2012 – 2013
Mersin Cement Plant
104.1. Installation of the HAC (Cement facility with Calcium aluminate )
Weight of the fabrication works: 485 ton
Weight of the installation works: 570 ton
Weight of the dismounting works: 120 ton
Insulation works: 295 m2
Cladding Works: 4500 m2
- VICAT – BASTAS BASKENT CIM. SAN. VE TIC. A.S. / 2013
Bastas Cement Plant
105.1. Installation and fabrication works for the Roller Press Unit ( BK - 2 )
Weight of the fabrication of the technological equipments: 161 ton
Weight of the fabrication of the steel construction: 877 ton
Weight of the fabrication of the mechanical equipments: 45 ton
Weight of the installation of the both technological and process
equipments: 1230 ton
Installation of the steel construction: 877 ton
Cladding works: 7600 m²
Insulation works: 3180 m²
- UZBEKISTAN DZHIZAK CEMENT FACTORY ( DAL TEKNIK ) / 2013
106.1. Fabrication of the paddle box for cement mill.
106.2. Fabrication of the temporary support for rotary kiln.
106.3. Fabrication of the support for the fan lines of the burner pipe.