1. RENAISSANCE CONSTRUCTION – RUSYA / 2012 – 2013  ( NORM-CCM )

Sebryakov Cement Plant  - Mihailovka

                       98.1. Fabrication and installation of the clinker production line ( 4000 Tpd. )

Site Fabrication

                       98.2. Fabrication of the cyclones and ducts: 1250 ton

                        Workshop Fabrication

                       98.3. Fabrication of the some equipments in our workshop located on

Ankara-TURKEY ( Light kiln sections of the rotary kiln,

Stacker-Reclaimer, Apron conveyor, belt conveyors: 600 ton).    

                       Erection

                       98.4. Erection of the raw mill unit.

                       98.5. Erection of the equipments in preheater tower.    

                       98.6. Erection of the rotary kiln unit.

            98.7. Erection of the clinker cooler unit and electrostatic precipitator for

clinker cooler.

                       98.8. Erection of the electrostatic precipitator for raw mill.

 

  1. RENAISSANCE CONSTRUCTION – RUSYA / 2012 – 2013  ( NORM-CCM )                                                                                                                                                                                                           

      Novocement Cement Plant-Novorosisky

                      99.1. Installation of the some units for clinker production line ( 4000 Tpd. )

                                   Total weight of the installation: 3000 ton.

 

  1.  KIPAS KAHRAMANMARAS CIMENTO SAN. TIC. A.S. / 2012 - 2013 - 2014

     Kahramanmaras Cement Plant

Fabrication and installation works for the clinker production line number II.

                      100.1. Fabrication of the steel structure: 6500 ton

                      100.2. Fabrication of the technological equipments: 4000 ton

                       (Casing of the filters, some parts for the clinker cooler, cyclones,   

               .       hoppers, gas ducts, chimney e.t.c. )      

                       100.3. Fabrication of the mechanical Equipments: 1500 ton   

(Casing of the coal, cement and raw mills, seperators, base frame of

the rollers for the rotary kiln, base frame of the roller press and their

accessories, valves, expansion joints, air slides and e.t.c.)     

                                   Total weight of the installation works: 15000 ton

                                   Insulation works: 20 000 m2

                                   Cladding works: 35 000 m2 

                       100.4. General installation works for air, water and lubrication.

 

  1.  DENIZLI CIMENTO SAN. TIC. A.S. / 2012

                  Denizli Cement Plant

                       101.1. Cladding works for the roof of the cement silo

                                       Weight of the fabrication works: 46 ton

                                       Weight of the installation works: 46 ton

                                       Weight of the dismounting works: 5 ton

                                       Cladding of the roof: 600m²

 

  1. RENAISSANCE CONSTRUCTION – RUSYA / 2012 – 2013  ( NORM-CCM )                                                                                                                                                                                                            

      Novocement Cement Plant-Novorosisky

                      102.1. Installation of the some units for clinker production line ( 4000 Tpd. )

                                   Total weight of the installation: 3000 ton.

 

 

 

  1.  CTP TEAM - S. KOREA / 2013

                   IGCC Gasfication Plant – Taean Project

                       103.1. Fabrication Mill Bag Filter Plenums

                                    Weight of the fabrication works: 75 ton

      

  1. CIMSA CIMENTO SAN. VE TIC. A.S. / 2012 – 2013

                  Mersin Cement Plant

                       104.1. Installation of the HAC (Cement facility with Calcium aluminate )

                                   Weight of the fabrication works: 485 ton

                                   Weight of the installation works: 570 ton

                                   Weight of the dismounting works: 120 ton

                                   Insulation works: 295 m2

                                   Cladding Works: 4500 m2

 

  1. VICATBASTAS BASKENT CIM. SAN. VE TIC. A.S. / 2013

                  Bastas Cement Plant

105.1. Installation and fabrication works for the Roller Press Unit ( BK - 2 )

                                   Weight of the fabrication of the technological equipments: 161 ton

                                   Weight of the fabrication of the steel construction: 877 ton

                                   Weight of the fabrication of the mechanical equipments: 45 ton

                                   Weight of the installation of the both technological and process

                                   equipments: 1230 ton                                                                                                                                                                                 

                                    Installation of the steel construction: 877 ton

                                  Cladding works: 7600 m²

                                  Insulation works: 3180 m²

 

  1. UZBEKISTAN DZHIZAK CEMENT FACTORY ( DAL TEKNIK ) / 2013

                       106.1. Fabrication of the paddle box for cement mill.

                       106.2. Fabrication of the temporary support for rotary kiln.

                       106.3. Fabrication of the support for the fan lines of the burner pipe.